The 20 largest AI data centers tracked by Epoch AI, ranked by the IT power Epoch estimates is in operation today. xAI's Colossus 2 in Memphis leads at 946 MW, just ahead of the Anthropic-Amazon campus in New Carlisle, Indiana, at 910 MW.

Estimated IT power in operation MW

Colossus 2946
New Carlisle910
Fairwater Atlanta636
DayOne Nusajaya473
Meta Prometheus471
DayOne Kempas422
Stargate Abilene421
Fairwater Wisconsin369

Estimates by Epoch AI (CC BY 4.0), dataset updated Oct 12, 2026

Chart: the eight AI data centers with the most estimated IT power in operation, as tracked by Epoch AI.

As of (Epoch AI dataset updated Oct 12, 2026)All figures are estimatesRanked: operational capacity onlyTies share a rank

Largest AI data centers tracked by Epoch AI, by estimated IT power in operation, as of 2026-10-13
Rank Data center Country Chip owner (per Epoch) IT power now (MW) Relative to #1 Compute (H100e, 8-bit dense) Epoch-projected build-out (MW IT, unranked)3 Figure
1 Colossus 25SpaceXAI United States SpaceXAI 946 1,112k 1,531 Q1 2027 Estimate
2 Anthropic-Amazon New Carlisle7Amazon · Project Rainier United States Amazon 910 686k 1,925 Q1 2028 Estimate
3 Microsoft Fairwater Atlanta9Microsoft · Microsoft AI WAN United States Microsoft 636 769k — Estimate
4 DayOne Nusajaya11Chip owner not listed Malaysia Not listed 473 584k — Estimate
5 Meta Prometheus12Meta · Prometheus United States Meta 471 536k 1,022 Q3 2028 Estimate
6 DayOne Kempas13Chip owner not listed Malaysia Not listed 422 481k — Estimate
7 OpenAI Stargate Abilene14Oracle · Stargate United States Oracle 421 509k 843 Q4 2026 Estimate
8 Microsoft Fairwater Wisconsin16Microsoft · Microsoft AI WAN United States Microsoft 369 446k 2,263 Q2 2028 Estimate
9 Google Pryor (North)18Google United States Google 368 637k — Estimate
10 Colossus 119SpaceXAI United States SpaceXAI 340 276k — Estimate
11 Google New Albany2Google United States Google 333 324k — Estimate
12 Google Columbus2Google United States Google 303 332k 386 Q3 2027 Estimate
13 Amazon Madison Mega Site2Amazon · Project Rainier (speculative) United States Amazon 284 214k 683 Q1 2028 Estimate
14 CoreWeave Denton TX2CoreWeave United States CoreWeave 262 253k 282 Q2 2027 Estimate
15 Bridge Data Centres MY062ByteDance (likely) Malaysia ByteDance (likely) 243 221k — Estimate
16 QTS Richmond 12Chip owner not listed United States Not listed 238 243k — Estimate
16 Google Bristow2Google United States Google 238 210k — Estimate
18 Google Council Bluffs (East)2Google United States Google 237 256k — Estimate
18 Google Omaha2Google United States Google 237 199k 395 Q3 2028 Estimate
18 Google Papillion2Google United States Google 237 101k — Estimate

Metric: Epoch AI's "Current power (MW)", which its hub labels IT power: the estimated power capacity of the computing equipment in the buildings Epoch judges to be operational at its latest dated observation, excluding cooling and other facility overhead.12 Epoch estimates it from cooling equipment counted in satellite imagery, permits and company statements; it expects 80% of its IT power estimates to fall within a factor of 1.4 of the true value.14 Total facility power is 20–50% higher, and actual average consumption is typically 60–80% of capacity, so "power draw" here means capacity, not metered use.1 Selection: the top 20 of the 94 sites in Epoch's dataset, which Epoch estimates covers 44% of global deployed AI compute as of Oct 13, 2026 (90% CI: 23% to 81%); sites it doesn't track (many smaller ones, and most outside the US) are missing, so this is a ranking of tracked sites, not a census.1 DayOne Kempas (421.7 MW in the file) ranks above Stargate Abilene (421 MW). Projected build-out is the highest future-dated IT power in Epoch's timeline for the site, with its quarter: Epoch's own projection from construction it can see, not an announcement, and never ranked; "—" means the timeline has no future-dated row.3 Chip owner is Epoch's "Owner" field (the owner of the AI chips); "likely" is Epoch's own confidence tag. Compute is Epoch's estimate in H100-equivalents, based on 8-bit peak performance with sparsity removed.4 Data: Epoch AI, AI data centers, CC BY 4.0. Figure labels: how they work.

The top 10

#1

Colossus 2

946 MW

xAI's second Memphis site, listed by Epoch under the owner SpaceXAI, with Anthropic, Cursor and SpaceXAI as users. Epoch estimates 946 MW of IT power across two operational buildings (1,276 MW of total facility power) and about 1.1 million H100-equivalents on Nvidia B200 and B300 chips.53 SpaceX's S-1 filing says the first cluster of about 110,000 GB200 processors and about 210 MW of compute power came online in 91 days, followed by 110,000 GB300 processors and 220 MW in 64 days.6 To power it quickly, xAI installed natural gas turbines just across the state line in Mississippi; Epoch projects 1,531 MW by Q1 2027.5

#2

Anthropic-Amazon New Carlisle

910 MW

Amazon's Indiana campus for Project Rainier, used by Anthropic. Epoch estimates 910 MW of IT power from 16 operational buildings and about 686,000 H100-equivalents on Amazon Trainium2 chips; like many Amazon sites, it has no external cooling plant and relies on direct air-based cooling, which makes it harder to read from above.74 Amazon describes Project Rainier as a cluster of nearly half a million Trainium2 chips and names St. Joseph County, Indiana, as one of its sites.8 Cleared land for 14 more buildings is why Epoch projects 1,925 MW by Q1 2028.3

Video: Amazon's official look inside Project Rainier, the AI compute cluster at New Carlisle (Amazon News channel). Operator video.
#3

Microsoft Fairwater Atlanta

636 MW

Built by QTS with Microsoft as the tenant in Fayetteville, Georgia, and likely used by OpenAI and Microsoft, per Epoch, which estimates 636 MW of IT power and about 769,000 H100-equivalents on Nvidia B200 chips.9 Epoch dates buildings 1 and 2 to October 2025 and buildings 3 and 4 to June 2026.3 Microsoft says the site began operating in October as the second Fairwater datacenter, with NVIDIA GB200 NVL72 racks, a two-story layout and liquid cooling, linked to its other Fairwater sites over a dedicated AI wide-area network.10 Epoch's timeline has no future-dated expansion for it.

#4

DayOne Nusajaya

473 MW

The highest-ranked site outside the United States, in Johor Bahru, Malaysia. Epoch doesn't know who owns the AI chips; it estimates 473 MW of IT power and about 584,000 H100-equivalents on Nvidia H100 and B300 chips, and leaves out the campus's three Phase 1 buildings because Phase 2 was reported as the first in the region built for large-scale AI computing.11 Its latest timeline entry (Oct 2, 2026) counts ten buildings as operational, an estimate based on the state of buildings 7–10 in April 2026 plus time to finish and ramp up.3

#5

Meta Prometheus

471 MW

Meta's cluster in New Albany, Ohio, which Epoch calls unusual for its ad hoc build: a patchwork of weatherproof tents, colocation facilities and conventional buildings along the business park. Epoch estimates 471 MW of IT power and about 536,000 H100-equivalents on Nvidia B300 chips.12 Its Aug 31, 2026 entry counts four tent buildings as running, from infrared drone video that also suggested about 138.8 MW of the on-site Socrates South gas plant's 200 MW nameplate was operating.3 Epoch projects 1,022 MW of IT power by Q3 2028.12

#6

DayOne Kempas

422 MW

A second DayOne campus in Johor, Malaysia, again with no chip owner listed by Epoch, which estimates 422 MW of IT power and about 481,000 H100-equivalents on Nvidia B300 chips.13 The figure rests on Epoch's assumption that buildings 7 and 8 were operational by Oct 1, 2026: they were roofed by March 2026 and their cooling and backup power looked complete in August, so Epoch allowed two months of commissioning. Its first estimate for the site was cross-checked against DayOne's report of 390 MW "in service" across its two Johor campuses in January 2026.3

#7

OpenAI Stargate Abilene

421 MW

The first Stargate site, in Abilene, Texas, with chips owned by Oracle and used by OpenAI. Epoch estimates 421 MW of IT power from four operational buildings and about 509,000 H100-equivalents on Nvidia B200 and B300 chips.14 The same timeline entry gives 590 MW of total facility power for those four buildings: the same estimate expressed two ways, IT load versus the whole facility including cooling, a ratio of 1.4, Epoch's default peak PUE outside the hyperscalers.34 Developer Crusoe says construction began in June 2024 and the planned campus has eight buildings.15 Epoch projects buildings 5–8 online around Nov 1, 2026, for 843 MW IT (1,180 MW facility).3

Video: Oracle's official video on its Abilene, Texas, data center, the first Stargate site (Oracle channel). Operator video.
#8

Microsoft Fairwater Wisconsin

369 MW

Microsoft's site in Mount Pleasant, Wisconsin, likely used by OpenAI and Microsoft. Epoch estimates 369 MW of IT power from one operational building and about 446,000 H100-equivalents on Nvidia B200 chips, dating Building 1 to April 16, 2026 from a Microsoft post.163 Microsoft describes 315 acres and three buildings with 1.2 million square feet under roof, cooled by a closed-loop liquid system.17 It carries the largest projection in this table: a revised nine-building plan behind Epoch's 2,263 MW by Q2 2028, though Epoch's methodology notes that an early run of its cooling model gave an unrealistic 1.5 GW here, having mistaken air-cooled condensers for cooling towers.34

#9

Google Pryor (North)

368 MW

Google's site in Pryor, Oklahoma, with Google DeepMind as a "speculative" user in Epoch's tags. Epoch estimates 368 MW of IT power and about 637,000 H100-equivalents on Google TPU v5p and v5e chips, more compute than several larger sites because the compute figure depends on the chips Epoch assumes.18 Its estimate jumped from 53 MW to 368 MW when Building 2, retrofitted from a warehouse, became operational in September 2026, confirmed by drone imagery of its cooling-tower fans spinning.3

#10

Colossus 1

340 MW

xAI's first Memphis cluster, built in a former Electrolux building, per Epoch, which estimates 340 MW of IT power and about 276,000 H100-equivalents on a mix of Nvidia H100, H200 and B200 chips.193 SpaceX's S-1 says the first cluster of about 100,000 H100 processors and about 130 MW of compute power came online in 122 days.6 Anthropic said in May 2026 that it had agreed to use all of the site's compute capacity, "more than 300 megawatts" and over 220,000 NVIDIA GPUs.203 Epoch projects no further growth.19

Sources

  1. Epoch AI, AI data centers (data hub and FAQ; dataset updated Oct 12, 2026; CC BY 4.0), retrieved 2026-10-13.
  2. Epoch AI, AI data centers CSV (fields "Current power (MW)", "Current H100 equivalents", "Owner", "Project", "Country"; CC BY 4.0), retrieved 2026-10-13.
  3. Epoch AI, AI data center timelines CSV (dated IT power, total power, buildings operational and construction notes; CC BY 4.0), retrieved 2026-10-13.
  4. Epoch AI, AI data centers documentation: Methodology, retrieved 2026-10-13.
  5. Epoch AI, Colossus 2 (directory entry, updated Oct 12, 2026), retrieved 2026-10-13.
  6. Space Exploration Technologies Corp., Form S-1 registration statement (SEC EDGAR), retrieved 2026-10-13.
  7. Epoch AI, Anthropic-Amazon New Carlisle (directory entry), retrieved 2026-10-13.
  8. Amazon, AWS activates Project Rainier: One of the world's largest AI compute clusters comes online, retrieved 2026-10-13.
  9. Epoch AI, Microsoft Fairwater Atlanta (directory entry), retrieved 2026-10-13.
  10. Microsoft, From Wisconsin to Atlanta: Microsoft connects datacenters to build its first AI superfactory, retrieved 2026-10-13.
  11. Epoch AI, DayOne Nusajaya (directory entry), retrieved 2026-10-13.
  12. Epoch AI, Meta Prometheus (directory entry), retrieved 2026-10-13.
  13. Epoch AI, DayOne Kempas (directory entry), retrieved 2026-10-13.
  14. Epoch AI, OpenAI Stargate Abilene (directory entry), retrieved 2026-10-13.
  15. Crusoe, Crusoe announces flagship Abilene data center is live, retrieved 2026-10-13.
  16. Epoch AI, Microsoft Fairwater Wisconsin (directory entry), retrieved 2026-10-13.
  17. Microsoft, Inside the world's most powerful AI datacenter (Sep 18, 2025), retrieved 2026-10-13.
  18. Epoch AI, Google Pryor (North) (directory entry), retrieved 2026-10-13.
  19. Epoch AI, Colossus 1 (directory entry), retrieved 2026-10-13.
  20. Anthropic, announcement of the SpaceX Colossus 1 agreement, retrieved 2026-10-13.